Commitment from NJ DOT on restoration timeline for Clarksville Road Bridge (Nov 04, 2026)


Clarksville Road (CR 638) over Amtrak 

Commitment from NJ DOT on restoration timeline for Clarksville Road Bridge
 

Now that Amtrak access has been achieved the entire project duration will take an estimated 9 months to complete.  Please note this timeline is heavily dependent on predictable and consistent outage windows being provided by Amtrak to NJDOT for the sub-structure repairs.  The Department is continuing to work with Amtrak to schedule these outages and maximize outage windows during the weekends to keep progressing the repair work. 

For awareness, the NJDOT began work on the bridge deck last week and sub-structure work commenced this past Friday and Sunday and will continue through Thursday of this week.