CLARKSVILLE BRIDGE UPDATES
Aug 14, 2026
|
Clarksville Road (CR 638) over Amtrak
- The designer and the County have been in communication regarding the traffic signals. Revisions were requested by the designer and are under review. Once finalized and approved, NJDOT’s Government and Community Relations team will reach out to the Township and County for recommendations and approvals.
- The utility company continues to work with Amtrak to arrange an on-site meeting to resolve the fiber optic line concerns.
- With the support of Amtrak, the contractor has taken measurements needed to continue fabrication work.
- A crew has continued field fabrication of the steel on site as progress continues.
|
July 31, 2026
|
Clarksville Road (CR 638) over Amtrak
|
July 2, 2026 |
Clarksville Road (CR 638) over Amtrak
- The Site-Specific Safety Work Plan (SSSWP) has been completed and submitted to Amtrak for review. Amtrak is actively reviewing the plan and providing comments as part of the project coordination process.
- NJDOT and Amtrak continue to coordinate closely on the project. This week, Amtrak supported contractor access to obtain additional field measurements and is scheduled to support the contractor during deck and deck joint repairs the week of July 13, 2026.
- The contractor continues with on-site steel fabrication, with approximately 35% of the stringer fabrication completed. The hi-rail equipment has successfully passed Amtrak's inspection and is on site, ready for use once work is authorized.
|
May 29, 2026 |
|
May 11, 2026
|
|
April 27, 2026 |
RESOLUTION SUPPORTING STATE FUNDING FOR THE REOPENING AND REPLACEMENT OF THE CLARKSVILLE ROAD BRIDGE
Resolution 2026-R091
|
March 23, 2026 |
Clarksville Road Bridge Update
Commissioner Priya Jain reached out to me today to confirm that all inspections by NJ DOT have been completed. According to original timeline it would take them four weeks to analyze the inspection results to come up with options to get the bridge repaired.
She promised to make every effort to expedite the process. I expect to hear back from her by next week on the progress and whether she was able to expedite the analysis to come up with possible options to consider.
|
March 20, 2026 |
Clarksville Road Bridge Update (March 20 2026)
|
March 02, 2026 |
Governors Packet for Clarksville Rd. Bridge Closure
|
Feb 21, 2026 |
Sign Petition - Repair the Clarksville Road Amtrak Bridge immediately
|
Feb 11, 2026 |
Bridge inspection work on Clarksville Road Bridge is scheduled to begin tonight, February 11, 2026, and continue through February 13, 2026. At this time, there are no updates regarding reopening or repair efforts. We will continue to provide updates as we have them.
|
| Feb 07, 2026 |
NJ12 coverage of Clarksville Road Bridge |
| Feb 05, 2026 |
Clarksville Bridge Update |
| Feb 03, 2026 |
Lack of Progress on Clarksville Road Bridge |